What is the total contract value of these four 2x800 MW projects, and how does this specific order intake impact BHEL’s current order book-to-bill ratio and revenue recognition visibility for the next 36-48 months?
Exact combined contract value cannot be confirmed from the cited disclosures. The announcements identify five 2x800 MW plants across four order announcements: Singrauli, Lara, Koderma, Raipur and Mirzapur. The only explicit combined contract value is over ₹7,000 Cr for the Raipur and Mirzapur projects [1]. The Koderma and Singrauli announcements confirm EPC awards but do not state their contract values in the cited passages [2] [3]. Lara’s cited ₹15,529.99 Cr is the NTPC project cost, not necessarily BHEL’s EPC contract value [4].
Order-book impact
BHEL’s latest quantified order book in the cited evidence was ₹2,60,300 Cr in Q1 FY27, equivalent to approximately 7.2x trailing revenue [5]. The four historical awards should not be added again as fresh Q2 FY27 order intake: the relevant awards were announced in FY24—Lara in August 2023, Singrauli in March 2024, and Koderma and the Raipur–Mirzapur orders in 2024 [6] [3] [2] [1]. Their remaining unexecuted value is therefore already embedded in the reported backlog to the extent these orders remained outstanding.
For scale, the disclosed Raipur–Mirzapur value of over ₹7,000 Cr would represent:
- More than 2.7% of the ₹2,60,300 Cr order book, derived from the two cited values [1] [5].
- More than 0.19x of Q2 FY27 TTM revenue, using TTM revenue of ₹37,781.5 Cr [7].
That is a counterfactual incremental impact, not the actual current change in BHEL’s book-to-bill ratio. If the ₹7,000 Cr had been newly booked rather than historical, the 7.2x ratio would have moved to roughly 7.4x, holding the revenue denominator constant. The latest Q2 FY27 order-book figure itself could not be confirmed in the cited evidence.
Revenue-recognition visibility: next 36–48 months
The orders materially support multi-year revenue visibility, but they do not translate into immediate revenue. The relevant mechanism is phased EPC execution—engineering, equipment manufacture, supply, erection, testing and commissioning—rather than recognition of the full order value on award.
The clearest disclosed schedule is for Lara: Unit 1 is targeted for completion within 48 months and Unit 2 within 52 months from the zero date [4]. That supports visibility through the requested 36–48-month period, with part of the execution potentially extending beyond 48 months. BHEL’s company-wide backlog was already described as providing multi-year visibility, with FY26 order book of ₹2,39,057 Cr against FY26 revenue of ₹33,782 Cr [8].
Analytical conclusion: these projects strengthen the duration and depth of BHEL’s backlog rather than create a new step-up in the current book-to-bill ratio. They provide a substantial execution pool for the next three to four years, but the revenue cadence will depend on project milestones, equipment dispatches, site readiness, customer approvals and commissioning. Project-wise billing schedules, percentage-of-completion data and the unexecuted balance of each order could not be confirmed, so the four projects’ exact contribution to revenue in each of the next 12–16 quarters cannot be quantified.
Does the scope of these four 2x800 MW projects encompass a full EPC (Engineering, Procurement, and Construction) contract, or is it limited to the BTG (Boiler, Turbine, Generator) package, and what are the stipulated milestone-based payment terms disclosed in the contract?
The available disclosures support a full EPC basis for Koderma and Singrauli, not a BTG-only award. However, the cited announcement for the Raipur and Mirzapur projects does not specify whether their scope is full EPC or limited to BTG; that distinction cannot be confirmed from the disclosed material.
Payment terms: The cited contract announcements do not disclose the milestone-based payment schedule—such as advance payment, engineering or manufacturing milestones, dispatch, erection, commissioning, or performance-guarantee payments. Accordingly, no payment percentages, milestone triggers, retention terms, or bank-guarantee conditions can be stated reliably from the available contract disclosure.
The key distinction is therefore:
- Koderma and Singrauli: explicitly identified as EPC awards.
- Raipur and Mirzapur: project orders are confirmed, but the available announcement is insufficient to classify them as full EPC or BTG-only.
- Milestone payments: could not be confirmed for any of the four projects from the cited disclosures.
| Project | Scope supported by disclosure | Conclusion |
|---|---|---|
| Singrauli Stage-III, 2×800 MW | BHEL said it would set up the plant on an Engineering, Procurement & Construction basis. [3] | EPC |
| Koderma, 2×800 MW | BHEL described the order from DVC as being for setting up the project on an EPC basis. [2] | EPC |
| Raipur, 2×800 MW | BHEL disclosed an order from Adani Power, but the cited announcement does not state whether it is EPC or BTG. [1] | Not confirmed |
| Mirzapur, 2×800 MW | BHEL disclosed an order from MTEUPPL, but the cited announcement does not state whether it is EPC or BTG. [1] | Not confirmed |
How do the projected EBIT margins for these large-scale thermal power orders compare to the historical average margins reported in BHEL’s 'Power' segment over the last eight quarters, considering the current competitive landscape for thermal EPC?
There is no evidence-based comparison yet between order-specific projected EBIT margins and BHEL’s Power-segment history. The cited material does not provide projected EBIT margins for the large thermal EPC orders, nor does it provide Power-segment EBIT margins for each of the last eight quarters. The closest defensible benchmark is BHEL’s consolidated EBIT margin, which averaged 7.6% on a simple quarterly basis and 8.8% on a revenue-weighted basis over Q3 FY25–Q2 FY27.
Eight-quarter EBIT benchmark
The calculation below is EBIT divided by consolidated revenue; it is not a Power-segment margin.
- Simple average: 7.6%, derived from the eight quarterly margins.
- Revenue-weighted average: 8.8%, derived from total EBIT of ₹5,905.7 Cr divided by total revenue of ₹67,050.8 Cr.
- Recent trajectory: margins were materially stronger in Q4 FY26 and Q2 FY27 than the eight-quarter average, but the series remains volatile because Q1 FY26 was loss-making.
How this applies to the thermal orders
The large orders identifiable in the cited material include the 3×800 MW Meja Stage-II EPC project worth over ₹21,000 Cr, with a 70-month completion schedule [25], and earlier 2×800 MW EPC awards for Koderma and Singrauli. The Koderma and Singrauli awards were secured through International Competitive Bidding [2] [3].
Accordingly:
- A project-level EBIT margin below 7.6% would be below the simple consolidated historical benchmark.
- A margin around 8.8% would be broadly aligned with the revenue-weighted consolidated benchmark.
- A margin above 8.8% would exceed that benchmark, but would require explicit evidence of better pricing, cost protection, execution efficiency or mix.
- These thresholds are reference points, not projected margins. Revenue recognition, subcontracting, escalation clauses, financing costs, warranty provisions and cost-to-complete estimates are not available for the orders.
Competitive landscape and margin quality
The bidding environment argues for caution in assuming that recent consolidated margins will automatically carry into new thermal EPC awards. The Koderma and Singrauli projects were won through ICB [2] [3], while an ash-handling package at Singrauli attracted four bidders and was awarded to Indure as the lowest bidder [26]. This is consistent with competitive pricing pressure, particularly in balance-of-plant and ancillary packages.
The long execution period of the Meja contract also increases exposure to labour, commodity, subcontractor and schedule risks. Conversely, any effective price-variation or escalation protection could improve margin resilience; recent reporting has highlighted such clauses as a feature of BHEL’s newer order book [27].
Analytical conclusion: the correct benchmark is currently a 7.6–8.8% consolidated EBIT range, not a reported Power-segment average. Until BHEL or an analyst report discloses order-specific margin assumptions, it would be premature to treat the recent 12.9–15.5% consolidated margins as the expected economics of the new thermal EPC awards. A brokerage has expressed an expectation of company-wide margin expansion through FY27–FY29E, but that is not an order-level projection [5].
| Quarter | Consolidated revenue (₹ Cr) | Consolidated EBIT (₹ Cr) | Derived EBIT margin |
|---|---|---|---|
| Q3 FY25 | 7,277.1 [9] | 344.27 [10] | 4.7% |
| Q4 FY25 | 8,993.4 [11] | 895.93 [12] | 10.0% |
| Q1 FY26 | 5,486.9 [13] | -440.50 [14] | -8.0% |
| Q2 FY26 | 7,511.8 [15] | 680.08 [16] | 9.1% |
| Q3 FY26 | 8,473.1 [17] | 686.06 [18] | 8.1% |
| Q4 FY26 | 12,310.4 [19] | 1,908.3 [20] | 15.5% |
| Q1 FY27 | 7,697.7 [21] | 636.12 [22] | 8.3% |
| Q2 FY27 | 9,300.4 [23] | 1,195.4 [24] | 12.9% |
Sources
- [1]BHEL bags two back-to-back orders for 2x800 MW Raipur and 2x800 MW Mirzapur Supercritical Thermal Power Plants | Official Website of Bharat Heavy Electricals Limited, New Delhi, India — Bhel, 2026-11-04T04:06:03.447717
- [2]BHEL secures order for 2x800 MW Koderma Supercritical Thermal Power Project | Official Website of Bharat Heavy Electricals Limited, New Delhi, India — Bhel, 2026-11-04T04:06:03.447717
- [3]BHEL bags order for 2x800 MW Singrauli Supercritical Thermal Power plant | Official Website of Bharat Heavy Electricals Limited, New Delhi, India — Bhel, 2026-11-04T04:06:03.447717
- [4]BHEL bags order from NTPC to set up thermal power plant in Chhattisgarh · Business Upturn — Businessupturn, 2026-11-04T04:06:03.447717
- [5]BHEL Shares In Focus As Dolat Capital Upgrades Rating, Raises Target Price After Q1 Results — Check Upside — NDTV Profit, 2026-07-17T00:00:00
- [6]Archived Announcements | Official Website of Bharat Heavy Electricals Limited, New Delhi, India — Bhel, 2026-11-04T04:06:03.447717
- [7]TTM Revenue INR
- [8]Bharat Heavy Electricals Limited Annual Report for FY 2025-26 — BSE India, 2026-07-09T00:00:00
- [9]Revenue INR
- [10]EBIT
- [11]Revenue INR
- [12]EBIT
- [13]Revenue INR
- [14]EBIT
- [15]Revenue INR
- [16]EBIT
- [17]Revenue INR
- [18]EBIT
- [19]Revenue INR
- [20]EBIT
- [21]Revenue INR
- [22]EBIT
- [23]Revenue INR
- [24]EBIT
- [25]BHEL secures Rs 21,000 crore Meja Stage-II EPC contract | Power Peak Digest — Powerpeakdigest, 2026-06-07T00:00:00
- [26]Contract Concluded.xlsx - Tenders - BHEL — Tenders, 2026-06-19T00:00:00
- [27]BHEL share price rallies 5% on huge volume; nears record high | Markets News - Business Standard — Business Standard, 2026-08-27T00:00:00
Keep digging