CORPORATE ANNOUNCEMENTOil Gas & Consumable Fuels

Indian Oil Corporation Ltd. makes a corporate announcement

Indian Oil Corporation Ltd.IOC

TL;DR

The disclosed project outlay is Rs 755 Crores for the 100 MW turnkey wind project, equivalent to Rs 7.55 Crores per MW on a derived basis. The order covers turbine supply, engineering, procurement and construction, project execution, and post-commissioning O&M; therefore, Rs 755 Crores is best treated as the total contract value, not necessarily pure capitalised project cost.

What is the total capital outlay for this 100 MW turnkey wind project, and how does this specific capacity addition align with the company's stated renewable energy capacity targets for FY25 and FY26 as outlined in the latest Annual Report or Investor Presentation?

The disclosed project outlay is Rs 755 Crores for the 100 MW turnkey wind project, equivalent to Rs 7.55 Crores per MW on a derived basis. The order covers turbine supply, engineering, procurement and construction, project execution, and post-commissioning O&M; therefore, Rs 755 Crores is best treated as the total contract value, not necessarily pure capitalised project cost. [1]

Alignment with IndianOil’s renewable-energy plans

  • FY25 baseline and long-term target: The FY25 investor presentation reported an existing renewable-energy portfolio of 252.1 MW and a target of 31 GW by 2030. It also identified Terra Clean Ltd. as the vehicle for developing 5.3 GW of renewable capacity. [2]
  • FY26 position: The FY26 Annual Report reported a renewable portfolio of 258.06 MW as of the year, comprising 167.60 MW of wind and 90.46 MW of solar; 5.95 MW of solar capacity was commissioned during FY26. [3]
  • Terra Clean execution pipeline: The FY26 Annual Report stated that development had commenced for 1 GW through Terra Clean, with preparatory work underway for an additional 4.3 GW—together representing 5.3 GW of planned/developing capacity on a derived basis. [4]

What the 100 MW means

  • Against the 5.3 GW Terra Clean plan: 100 MW represents approximately 1.89%, derived from 100 MW divided by 5,300 MW.
  • Against the broader 31 GW target: It represents approximately 0.32%, derived from 100 MW divided by 31,000 MW.
  • Against the installed portfolio: It is sizeable relative to the operating base—approximately 39.67% of the FY25 portfolio of 252.1 MW and 38.75% of the FY26 portfolio of 258.06 MW, both derived comparisons. [2] [3]

Analyst read: The project is strategically consistent with IndianOil’s renewable-energy expansion, but it is only a small increment against the company’s multi-gigawatt ambitions. It is material relative to the existing installed base, yet should not be counted as FY25 or FY26 commissioned capacity: the 100 MW order was announced in September 2026, after FY26 year-end, and no commissioning date is disclosed. The order announcement also does not establish whether this capacity is included within Terra Clean’s 5.3 GW programme; that scope linkage remains unreported.

How is this project structured from an accounting perspective—specifically, is it being capitalized as a direct asset on IOCL's balance sheet, or is it structured as a long-term Power Purchase Agreement (PPA), and how does this classification affect the company's projected depreciation and return on capital employed (ROCE) for the renewable energy segment?

The project-specific accounting treatment cannot be confirmed as either direct IOCL-owned PPE or a pure long-term PPA from the reported disclosures. More importantly, the renewable programme appears to use multiple structures: the 650 MW round-the-clock requirement is being progressed through IndianOil NTPC Green Energy Pvt. Ltd. (INGEL), a joint venture, while the larger 1 GW development programme is being pursued through wholly owned subsidiary Terra Clean Ltd. [5] [6]

What is established

  • IOCL reports a renewable portfolio of 258.06 MW as of FY26, comprising 167.60 MW of wind and 90.46 MW of solar, which generated 371.40 GWh during the year. [5]
  • INGEL is progressing renewable capacity to meet refinery expansion requirements and was stated to be on course to commission 50 MW during the year; this sits within the broader 650 MW round-the-clock renewable power requirement. [3]
  • Terra Clean, IOCL’s wholly owned subsidiary, has commenced pre-project work for 1 GW of renewable capacity and secured approvals for a further 4.3 GW. [3]
  • IOCL’s accounting policy states that assets under construction are carried as capital work in progress, construction-period expenses and eligible borrowing costs are capitalised, and PPE is subsequently carried at cost less accumulated depreciation and impairment. [7] [7] [7]

The annual report does not report project-level capex ownership, PPA terms, useful lives, commissioning dates, or a renewable-specific depreciation and ROCE forecast. Its segment reporting places power generation within “Other Business Activities”, but does not separately disclose renewable depreciation or renewable ROCE. [8] [9]

Accounting impact by structure

A PPA should not automatically be treated as off-balance-sheet: contract terms would need to be examined for any identified-asset, control or lease-like features. Likewise, the existence of INGEL as a JV means the relevant choice is not necessarily limited to “IOCL PPE versus PPA”.

Implication for renewable ROCE

The current evidence supports no defensible numerical projection for renewable-segment depreciation or ROCE. The key variables are:

1. Who owns the generation asset—IOCL, INGEL, Terra Clean or another project company; 2. Whether the project is consolidated or equity-accounted; 3. The amount capitalised and commissioning date; 4. Useful life and depreciation method; 5. PPA tariff, plant-load factor and operating costs; and 6. Whether “capital employed” includes project debt and CWIP.

If the project is direct PPE, expect a front-loaded ROCE drag during construction and early operations because the capital base precedes full earnings. If it is a straightforward PPA, depreciation and capital employed would be lower at IOCL, but the power cost would flow directly through operating profit. The present disclosures therefore support a structure-dependent ROCE outcome, not a confirmed depreciation or ROCE forecast.

StructureBalance-sheet treatmentDepreciation effectROCE effect
Direct IOCL-owned renewable assetCapex accumulates in CWIP and becomes PPE when commissioned. [7]No depreciation during construction; depreciation begins when the plant is available for use.Capital employed rises immediately, while earnings build with utilisation and contracted tariffs. Initial segment ROCE would therefore be diluted, with improvement dependent on generation and margins.
PPA with no control or ownership of the plantIOCL would generally carry no generating-plant PPE; power purchases would be recognised as operating costs as incurred.No plant depreciation for IOCL.Lower capital employed supports a mechanically higher ROCE denominator profile, but the recurring PPA expense reduces operating profit. The net effect depends on tariff and operating profitability.
JV or subsidiary-owned projectThe treatment depends on whether the entity is equity-accounted or consolidated. An equity-accounted JV would not place the underlying plant line-by-line on IOCL’s standalone balance sheet; a consolidated subsidiary would appear in group assets but not necessarily in standalone IOCL PPE.Depreciation would arise at the project entity if it owns the plant, but its visibility would differ between standalone and consolidated accounts.Standalone IOCL ROCE could understate or omit project operating capital, while consolidated ROCE would capture the relevant asset and earnings only according to the applicable consolidation method.

Sources

  1. [1]Inox Wind bags ₹755-crore turnkey project from IOCThe Hindu BusinessLine, 2026-09-03T00:00:00
  2. [2]Indian Oil Corporation Investor Handout: Strategic Overview, Green Initiatives, and Major Capex Plans.2025-06-02T07:01:51.197000, p.3
  3. [3]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.108
  4. [4]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.21
  5. [5]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.75
  6. [6]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.12
  7. [7]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.211
  8. [8]Unaudited Financial Results for the Quarter Ended June 30, 20262026-07-31T17:43:03, p.7
  9. [9]Unaudited Financial Results for the Quarter Ended June 30, 20262026-07-31T17:43:03, p.15
  10. [10]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.139
  11. [11]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.81
  12. [12]Integrated Annual Report 2025-26 for Indian Oil Corporation Limited2026-08-07T11:23:13.743000, p.39

Keep digging

What is the total capital outlay for this 100 MW turnkey wind project, and how does this specific capacity addition align with the company's stated renewable energy capacity targets for FY25 and FY26 as outlined in the latest Annual Report or Investor Presentation?

Ask Copilot
Logo

Unlock financial AI for your firm